Overview
on Sediment Management and Assessment
Thomas Fredette, US Army Corp of Engineers, New
England District, Concord, MA
Remediation
of the New Bedford Harbor Superfund Site
Steve Wolf, ENSR, Westford, MA
Excavation
of PCB-Contaminated Sediment Adjacent to the Intake of a
12-MGD Drinking Water Plant
Bryan R. Maurer, Cummings/Riter Consultants, Inc.,
Pittsburg, PA
Effectiveness
of in situ Cement Stabilization for Remediation of
Sediment Containing Coal Tar Derived Hydrocarbons
Chris Leuteritz, Anchor Environmental, LLC, Andover, MA
Monitoring
the Uplift of a Low-Permeability Sediment Cap Due to Gas
Entrapment Beneath the Cap: Findings of the First 18
Months
Robert D. Mutch Jr., HydroQual, Inc., Mahwah, NJ
Optimization
of PCB Dechlorination by Palladized Magnesium in Marine
Sediments
Irina Calante, University of New Hampshire, Durham, NH
Excavation
of PCB-Contaminated Sediment Adjacent to the Intake of a
12-MGD Drinking
Water Plant
Bryan R. Maurer, P.E., Cummings/Riter Consultants,
Inc., 10 Duff Road, Suite 500, Pittsburgh, PA, 15235, Tel:
412-241-4500, Fax: 412-241-7500, Email: bmaurer@cummingsriter.com.
The ROD for the former Westinghouse plant in Sharon,
Pennsylvania issued in February 2003 included the removal
of approximately 4,000 CY of PCB-contaminated sediment
from several locations along the Shenango River to a
cleanup goal of 1.0 mg/kg.
Delineation sampling indicated a maximum total PCB
concentration of about 400 mg/kg, although 97% of the
sediment samples were less than 50 mg/kg, and 88% of the
samples were less than 10 mg/kg. Remediation planning was complicated by the presence of a 12
MGD drinking water plant with a surface intake less than
200 feet from the remediation areas, along with an active
24-inch cast iron water line crossing the river underneath
the riverbed. Given
the water depth and composition of the riverbed, as well
as potential flow velocities during high flow periods, it
was determined that the best means of protecting the water
plant intake during the remediation would be to isolate
the excavation areas using sheet piling, with placement of
silt screens around the intake as well as downstream of
the pile installation areas.
In addition, a mobile laboratory was brought on
site to provide rapid analysis of surface water samples at
quantitation limits of 0.05 ug/l, in order to provide
reassurance to all interested parties that the water
supply would not be impacted by the work.
Remediation commenced in summer 2004, and to date, more than
800 surface water samples have been collected downstream
of active work areas, including more than 300 samples
collected directly from the water plant intake.
No PCBs have been detected in any of the water
samples collected from the intake, and only five other
samples collected downstream of work areas were found to
contain PCBs (up to 0.26 ug/l).
The sediment remediation, delayed by Hurricanes
Frances and Ivan, is expected to be completed in spring
2005.
Effectiveness
of in situ
Cement Stabilization for Remediation of Sediment
Containing Coal Tar Derived Hydrocarbons
Todd Thornburg, Anchor Environmental, L.L.C., 6650 SW Redwood
Lane, Suite 110, Portland, OR, 97224, Tel: 503-670-1108,
Fax: 503-670-1128, Email: tthornburg@anchorenv.com
Chris Leuteritz, Anchor Environmental, L.L.C., 2
Dundee Park, Suite 102, Andover, MA 01810, Tel:
978-474-9090, Fax: 978-474-9080, Email:
cleuteritz@anchorenv.com
David Templeton, Anchor Environmental, L.L.C., 1423 Third
Avenue, Suite 300, Seattle, WA, 98101, Tel: 206-287-9130,
Fax: 206-287-9131, Email: dtempleton@anchorenv.com
Tim Metcalf, Honeywell International Inc., 101 Columbia
Road, Morristown, NJ, 07962-1139, Tel: (973) 455-4107,
Fax: (973) 455-3082, Email: tim.metcalf@honeywell.com
Tracey Bell, KeySpan
Energy, One Metrotech Center, 15th Floor, Brooklyn, NY
11201-3850, Tel: (718) 403-3053, Fax: (718)
222-1546, Email: tbell@keyspanenergy.com
Kurt Paschl, Beazer
East, Inc., One Oxford Centre, Suite 3000, Pittsburgh, PA,
15219-6401, Tel: (412) 208-8863, Fax: (412) 208-8869,
Email: paschlk@hansonle.com
Sediments adjacent to a former coal tar processing facility
are associated with intermittent releases of hydrocarbon
droplets and sheen to the overlying marine water column,
particularly during low tide.
In situ
sediment stabilization with Portland cement was one of the
alternatives considered for a response action to control
sheen in accordance with Surface Water Quality Standards.
The remedial design concept consisted of driving
large-diameter caissons through the sediment and into the
underlying clay aquitard, mixing Portland cement inside
the caissons (approximately 15 percent by weight) using an
auger or similar piece of equipment, and removing minor
amounts of surficial sediment that had bulked up above the
original mudline. The caissons would then be pulled,
offset in a systematic overlapping pattern, and the
process repeated until the sheen-producing area had been
stabilized.
Bench-scale laboratory testing was conducted on composite
samples of both untreated and stabilized sediments from
the area to better characterize the effectiveness of
cement stabilization for controlling sheen.
The bench-scale tests included the Sequential Batch
Leaching Test (SBLT), a U. S. Army Corps of Engineers
protocol (Myers et al., 1992) that simulates the effects
of contaminated sediment on pore-water chemistry, and a
more qualitative Static Sheen Test, per USEPA (40 CFR
Chapter 1, Part 435).
Tests were conducted on sediments treated with 10,
15, and 20 percent dry cement, 15 percent cement slurry,
and, for comparison, 10 percent organoclay, a hydrocarbon
adsorbent. Sediment
mixtures were allowed to cure for seven days before
testing.
The bench-scale test results indicate in situ stabilization as a stand-alone technology would not be
effective at controlling sheen; the response action would
require additional components, such as the addition of a
thick cap or placement of sediments in a confined disposal
facility, to achieve this objective.
Even the most effective stabilization mixtures
leached polycyclic aromatic hydrocarbons (PAHs) and
mid-range aromatic and aliphatic hydrocarbons at
concentrations well above their effective solubilities,
indicating a strong tendency for continued sheen
production. Performing
the appropriate bench-scale tests cost-effectively
demonstrated the need for a different approach to
designing and implementing an effective remedial solution
for this site.
Monitoring
the Uplift of a Low-Permeability Sediment Cap Due to Gas
Entrapment Beneath the Cap: Findings of the First 18
Months
Robert D. Mutch, Jr., P.Hg., P.E. (MSCE) and Egon
Weber, Ph.D., HydroQual, Inc., 1200 MacArthur Blvd.,
Mahwah, NJ 07430, Email: rmutch@hydroqual.com
Daniel Kearney, P.E. (MSCE), Brown and Caldwell, Inc., 100
Commerce Drive, Allendale, NJ
07456, Email: dkearney@brwncald.com
The Hazardous Substances Research Center (HSRC), in
conjunction with Battelle, Horne Engineering, and
HydroQual, Inc., is conducting a major field study of
“active” sediment caps on the Anacostia River near
Washington, DC. As a part of this overall study, the
potential uplift and deformation of low-permeability
sediment cap constructed with AquaBlokTM is
being studied using highly sensitive, in-place horizontal
inclinometers. The potential for low permeability sediment
caps to be uplifted by increases in sediment pore
pressures due to the designed restriction of groundwater
discharge caused by the cap or by transient tidal
fluctuations has been shown to be significant in some
riverine and estuarine settings. Uplift could potentially
cause cracking and jointing of the low permeability cap
substantially increasing its hydraulic conductivity and,
consequently, compromising the cap’s ability to restrict
contaminant flux.
The research project involves construction of several pilot
scale sediment caps. One such pilot scale sediment cap
consists of six inches of AquaBlokTM overlain
with six inches of sand. A 100-foot long horizontal
inclinometer casing was constructed within the 100 by 80
foot pilot-scale cap overlying the AquaBlokTM.
A string of ten in-place horizontal
inclinometers is housed in the casing and has been
measuring uplift or deformation of the cap since March 26,
2004. The data have recorded initial settlement of the cap
due to sediment consolidation. Following initial
settlement, the further offshore portion of the cap began
to slowly uplift a total of about one inch over a period
of 40 days before suddenly uplifting more than two feet.
Uplift events of similar magnitude occurred intermittently
throughout the summer and early fall of 2004. Initial
indications point to instability caused by a buildup of
decomposition gas from the sediments under the cap.
Bathymetric surveys have revealed that the cap is thinner
in the area of observed instability. The cap has been
relatively dormant during the late fall and winter likely
corresponding to declining temperatures and concomitant
reductions in gas generation. Monitoring will continue
throughout 2005 to observe whether a renewed cycle of
uplift events occurs when temperatures rise again in the
spring and summer.
Optimization
of PCB Dechlorination by Palladized Magnesium in Marine
Sediments
Irina Calante, University of New Hampshire, 330 Gregg Hall, 35 Colovos Rd., Durham, NH,
03824, Tel: 603-862-1197, Fax: 603-862-3957, Email:
Icalante@unh.edu
Kevin H. Gardner, University of New Hampshire, 336 Gregg
Hall, 35 Colovos Rd., Durham, NH, 03824, Tel:
603-862-4334, Fax: 603-862-3957, Email: Kevin.Gardner@unh.edu
Jeannie C. Spear, University of New Hampshire, 222 Gregg
Hall, 35 Colovos Rd., Durham, NH, 03824, Tel:
603-862-1445, Fax: 603-862-3957, Email: Jeannie.Spear@unh.edu
Emese Hadnagy, University of New Hampshire, 330 Gregg
Hall, 35 Colovos Rd., Durham, NH, 03824, Tel:
603-862-1197, Fax: 603-862-3957, Email: Ehadnagy@unh.edu
Currently, marine sediments contaminated with Polychlorinated
Biphenyls (PCBs) are treated ex-situ through dredging
followed by landfill.
This form of treatment can be very costly, has high
impacts on the marine environment, and can further disturb
and disperse PCBs from the sediments. Capping and
monitored natural recovery are two other viable options,
both of which suffer from leaving contamination in place.
This research focuses on the optimization of in-situ
treatment of marine sediments contaminated with PCBs by
dechlorination with palladized magnesium.
Three sediments (New Bedford Harbor, MA, Housatonic
River, MA, and Hudson River, NY) have been tested for
dechlorination with palladized magnesium (4 mm magnesium
particles coated with 0.1% by weight palladium).
High PCB removals were observed for sandy sediments
with low organic carbon content, whereas lower removals
where seen for sediments with higher organic carbon
content. Desorption
experiments using Tenax beads were conducted to see
whether PCB desorption from sediment was a rate limiting
step for dechlorination.
Sediment characteristics such as PCB concentration,
organic carbon content, particle size distribution and
water content are being used to optimize the percent
addition of palladized magnesium to each sediment.
A study will also be conducted to see how well the
solvent d-Limonene extracts PCBs from the sediment and
makes them available to react with the palladized
magnesium. The results from these studies will be presented.
Top
|