|
Liability
Management at a Fuel Pipeline Release Site
Kiran
K. Srinivasan, ENTRIX, Inc., 5252 Westchester, Suite 250,
Houston, Texas 77005, Tel: 713-662-1920, Fax:
713-666-5227, Email: ksrinivasan@entrix.com
Christina Robinson, ENTRIX, Inc., 5252 Westchester, Suite
250, Houston, Texas 77005, Tel: 713-662-1912, Fax: 713-666-5227, Email: crobinson@entrix.com
A
landowner reported a leak in a subsurface fuel pipeline
located on remote, uninhabited farmland.
The landowner perceived a delay by the company in
responding to the release and expressed dissatisfaction.
Subsequently, a fire of suspicious origin occurred
at the site. The
fire and associated safety concerns resulted in extensive
emergency response actions by the company.
A large area was excavated to isolate and repair
the pipeline and prevent product migration via a proximal
ditch. However,
the excavated, contaminated soils were stockpiled on bare
ground without any measures to prevent contaminant
leaching or runoff. The
landowner filed a lawsuit against the company alleging
that the initial response and subsequent actions were
intentionally delayed and thus harmed his interests.
The lawsuit resulted in further delays as
protracted negotiations were required with the landowner
and his legal counsel to obtain site access.
Meanwhile, the open excavation collected water from
several rain events, creating a potential for
contamination to migrate and infiltrate.
Also, contaminated stormwater now needed to be
addressed. As an added complication, the landowner hired a consultant
who undertook site and regulatory actions that conflicted
with the company’s actions.
Because of these developments, the agency increased
its scrutiny of an already high-profile project.
During the site investigations, the landowner’s
consultant remained onsite to observe and collect split
samples. Extensive
negotiations were required with the state agency and the
landowner’s counsel before remedial actions could be
initiated. Because
the company lacked a plan for expeditiously assessing and
addressing potential liability at release sites, it found
itself in a reactive mode.
Such a lack of liability planning resulted in
significant project schedule delays and cost overruns.
Had a plan existed to address landowner concerns
and undertake prompt action to mitigate contamination
expeditiously, issues related to schedule, cost and public
relations could have been better managed. The lawsuit and remedial actions are ongoing.
Top
|